Submit revised and additional information
Only resubmit your response when all the information answering the full report, is available and ready to submit at the same time. Submitting piecemeal, delays the process until all the required information has been received.
Provide a separate statement explaining how you have answered the points raised in the BSS report. Ideally, use the BSS report to add your answer for each point raised – include specific drawing numbers and specification note numbers to identify and locate the changes.
You must use the correct Council reference number. For example, 24/12345/WARR.
Drawing revisions must be either numbers or letters only. Do not combine numbers and letters for example, Revision A/1 as this causes an issue for the assessing surveyor.
Ensure the drawing number, revision and drawing description fields on the portal are separately populated with the relevant information only. Do not repeat the same information in each field as this displays incorrectly for the assessing surveyor.
Further guidance can be found in the following Scottish Government publications: