Project stages and dates
Phase 1 – Seals Craig to Hawes Car Park
6 October 2025 for approximately 8 to 10 weeks (see Latest News for update)
-
Re-surfacing and pavement widening
-
Minimal traffic management in place with no reduction in parking during works
Work will then pause for the busy Christmas period.

Phase 2 - Main High Street works
Starts February 2026 for approximately 12 months, working along the High Street in phases.
A contractor has now been appointed and there will be opportunities to meet with the contractor to hear about the detailed work programme.
Phase 2a

Phase 2b